Blog

1 Comment

  1. Jason

    Clarification: The BCWS (not the BCWP) reflects both the scheduled work (schedule baseline) AND the budget (cost baseline). The BCWS is fixed at the beginning of the project (only changed, as you pointed out, via EAC calculation).
    Also, the CPI reflects the BCWP return we get for every dollar we put in to the project (e.g. CPI of .80 means we earn/complete .80 of value for every dollar we spend (ACWP)).
    I wish Microsoft would move to the modern terminology.
    Thanks for the article. Cheers!

Leave a Comment