How to reassign a task to another resource?
,

How to reassign a task to another resource?

The best way to replace a resource is through the assign resources window:

  • Click Resource tab > Assign Resources
  • Select the old resource
  • Click Replace
  • Select the new resource
  • Click OK > Close

Get our ‘best practices template’ now!

Of course you can also deselect the old resource and select the new resource in the Resource Names column, but MS Project will see this as two separate actions: MS Project will first delete the old assignment (with the set %), then create a new assignment based on the max units for that resource and any part-time % for the task you had set will be gone.

Replace resources for the entire schedule

This is per assignment. If you want to replace a resource for the entire schedule, select all tasks for which you want to replace the resource. If you get the question ‘The task is 100% complete. Do you want to move the actual work to the new resource?’, it means that you selected a completed task. Click cancel and deselect the completed tasks. All tasks with 0% completion and the remaining parts of partially completed tasks are reassigned.